Road Rehabilitation & Maintenance

The City of Niagara Falls uses a pavement information system to determine which streets will be capital improvements in any given year. Pavement conditions, pavement age, traffic volumes, timely maintenance and work are all monitored and ultimately influence the timing and need for road rehabilitation projects.

2022 Budget Year will see 22 km of roads rehabilitated through the capital programs that include road resurfacing, overlay and restoration programs. That includes 13 km of Urban Roads reconstructed and / or resurfaced, and 9 km of Rural Roads surface treated. Additionally, 11 km of sidewalks and curbs will be replaced.

The streets selected for road improvements have been listed below. The work on each street will take about six to eight weeks from start to finish. Construction will take place in stages and there may be delays between each stage.

Please note that streets could be added to or deleted from the program without prior notice from the City.

Beechwood Road

Scope of Work

From Lundy's Lane to McLeod Rd

When will the work take place?

Summer 2022

Associated Project

The following project is associated with this  Surface Treatment Program 2022

Casey Street

Scope of Work

From Olden Ave. to Dorchester Rd.

When will the work take place?

Spring/Summer 2022

Associated Project

The following project is associated with this  Road Rehabilitation Program 2022

Charnwood Avenue

Scope of Work

From Montrose Rd to Tad St

When will the work take place?

Spring/Summer 2022

Associated Project

The following project is associated with this  Road Rehabilitation Program 2022

Crowland Avenue

Scope of Work

From Lincoln to Netherby Rd.

When will the work take place?

Summer 2022

Associated Project

The following project is associated with this  Surface Treatment Program 2022

Drummond Road

Garner Road

Scope of Work

From McLeod Rd to Lundy's Lane

When will the work take place?

Summer 2022

Associated Project

The following project is associated with this  Surface Treatment Program 2022

Garner Road

Scope of Work

Hendershot Blvd to 150m Northwards

When will the work take place?

Summer 2022

Associated Project

The following project is associated with this  Surface Treatment Program 2022

Houck Drive

Scope of Work

From Valley Way to Slater Ave

When will the work take place?

Summer 2022

Associated Project

The following project is associated with this  Surface Treatment Program 2022

Kalar Road

Scope of Work

From Thorold Stone Road to 190m south of Niven St.

When will the work take place?

Spring/Summer 2022

Associated Project

The following project is associated with this  Mill & Pave Program 2022

Main Street

Scope of Work

From Ferry St to North St

When will the work take place?

Spring/Summer 2022

Associated Project

The following project is associated with this  Mill & Pave Program 2022

Norton Street

Scope of Work

From Portage Rd to Front St

When will the work take place?

Summer 2022

Associated Project

The following project is associated with this  Surface Treatment Program 2022

Oakwood Drive

Scope of Work

From Battlefield to QEW W/M Crossing

When will the work take place?

Spring/Summer 2022

Associated Project

The following project is associated with this  Mill & Pave Program 2022

Oxford Street

Scope of Work

From Rolling Acres Dr to Dorchester Rd

When will the work take place?

Spring/Summer 2022

Associated Project

The following project is associated with this  Road Rehabilitation Program 2022

Portage Road

Scope of Work

From O'Neil to Mountain Rd

When will the work take place?

Spring/Summer 2022

Associated Project

The following project is associated with this  Mill & Pave Program 2022

Portage Road

Scope of Work

Oakhall Entrance to Norton St

When will the work take place?

Spring/Summer 2022

Associated Project

The following project is associated with this  Mill & Pave Program 2022

President Drive

Scope of Work

Off Casey St

When will the work take place?

Spring/Summer 2022

Associated Project

The following project is associated with this  Road Rehabilitation Program 2022

Rosedale Drive

Scope of Work

From Slater Ave to Florence Ave

When will the work take place?

Summer 2022

Associated Project

The following project is associated with this  Surface Treatment Program 2022

Ross Street

Scope of Work

The engineering design for sewer separation, watermain replacement and road reconstruction on Ross Street.

When will the work take place?

Summer 2019

Associated Project

The following project is associated with this  Ross Street Sewer Separation - Design

Sixth Avenue

Scope of Work

From Jepson St to Rosedale Dr

When will the work take place?

Summer 2022

Associated Project

The following project is associated with this  Surface Treatment Program 2022

Slater Avenue

Scope of Work

From Jepson St to McRae St

When will the work take place?

Summer 2022

Associated Project

The following project is associated with this  Surface Treatment Program 2022

Swayze Drive

Scope of Work

From Johnson to Heritage Dr

When will the work take place?

Spring/Summer 2022

Associated Project

The following project is associated with this  Mill & Pave Program 2022

Twidale Avenue

Scope of Work

From Jepson St to Houck Dr

When will the work take place?

Summer 2022

Associated Project

The following project is associated with this  Surface Treatment Program 2022

Victoria Avenue

Scope of Work

Clark Avenue to Stanley Avenue. Design of underground sewer and watermain replacements, full road reconstruction with streetscaping, street furniture and LED street lighting.

Associated Project

The following project is associated with this  Victoria Avenue Streetscaping Revitalization Phase 3 Design

Associated Projects

ProjectDetails
Victoria Avenue Streetscaping Revitalization Phase 3 DesignDetails
Fallsview Boulevard Reconstruction Phase 1 ConstructionDetails
Garner Road Sanitary Extension Design - Black Forest Cr to Forestview BvDetails
Ross Street Sewer Separation - DesignDetails
Asset Management Plan UpdateDetails
Forestview Estates Subdivision Sanitary Sewer and Watermain UpsizingDetails
Beck Road Bridge ReplacementDetails
Drummond Road ImprovementsDetails
2021 Main Street Chippawa Road Reconstruction & Storm Sewer ReplacementDetails
Willoughby Drive ReconstructionDetails
Banting Avenue & Roosevelt Avenue Sanitary Sewer and Watermain ReplacementDetails
Willinger Street Watermain ReplacementDetails
Victoria Avenue BridgeDetails
Silvertown Area Functional Servicing Assessment StudyDetails
Chippawa Parkway Culvert ReplacementDetails
North Street Watermain ReplacementDetails
Portage Road & Prospect Street Sewer SeparationDetails
Marshall Road Bridge ReplacementDetails
Ort Road Bridge ReplacementDetails
Huron Street Road ReconstructionDetails
Armoury Street Sewer SeparationDetails
Elm Street Sewer SeparationDetails
Homewood Avenue Sewer SeparationDetails
Maple Street Sewer SeparationDetails
Drummond Road (Phase I) Watermain Replacement and Road Reconstruction from Thorold Stone Road to Cherrywood RoadDetails
Fallsview Boulevard Reconstruction - Phase 2 ConstructionDetails
Rideau Street Watermain ReplacementDetails
Schisler Road Bridge RehabilitationDetails
Detenbeck Road Bridge ReplacementDetails
Koabel Road Bridge RehabilitationDetails
Major Donald Dell Bridge RehabilitationDetails
Willowdell Road Bridge RehabilitationDetails
Garner Road Reconstruction - McLeod Road North to Hydro CorridorDetails
Dorchester Road Reconstruction (Oldfield to Mcleod)Details
Dorchester/Oldfield Intersection EA & DesignDetails
Dixon Street Sewer Separation (Level Ave. to Orchard Ave.)Details
Surface Treatment Program 2022Details
Mill & Pave Program 2022Details
Road Rehabilitation Program 2022Details
Reixinger Road Watermain Loop and Hospital ServicingDetails
Mewburn Road Reconstruction - Mountain Road North to City LimitsDetails
Victoria Avenue & Bridge Street RoundaboutDetails
Rural Roads Needs StudyDetails
Whirlpool Road Reconstruction - OPG Canal to Stanley AvenueDetails
Royal Manor Drive Bridge RehabilitationDetails
Stanley Business Park Watermain Replacements Phase 1Details
Willick Road Reconstruction - Sodom Rd. to Ort Rd (Design)Details
Willick Road Box Culvert ReplacementDetails