Road Rehabilitation & Maintenance

The City of Niagara Falls uses a pavement information system to determine which streets will be capital improvements in any given year. Pavement conditions, pavement age, traffic volumes, timely maintenance and work are all monitored and ultimately influence the timing and need for road rehabilitation projects.

2024 Budget Year will see 24.6 km of roads rehabilitated / reconstructed through the capital programs including road reconstruction, resurfacing, overlay and restoration programs. That includes 14.4 km of Urban Roads reconstructed and / or resurfaced, and 10.2 km of Rural Roads surface treated. Additionally, 1.3 km of sidewalks and curbs will be replaced.

The streets selected for road improvements have been listed below. The work on each street will take about six to eight weeks from start to finish. Construction will take place in stages and there may be delays between each stage.

Please note that streets could be added to or deleted from the program without prior notice from the City.

Armoury Street

Scope of Work

Between Victoria Ave. and Crysler Ave.

When will the work take place?

Spring / Summer 2023

Associated Project

The following project is associated with this  Armoury Street Sewer Separation

Bossert Road

Scope of Work

From King Road to Bossert Service Road

When will the work take place?

Spring / Summer 2024

Associated Project

The following project is associated with this  2024 Surface Treatment Program

Bossert Service Road

Scope of Work

From Bossert Road to Ort Road

When will the work take place?

Spring / Summer 2024

Associated Project

The following project is associated with this  2024 Surface Treatment Program

Cardinal Drive

Scope of Work

From Montrose Road to Thorold Stone Road

Associated Project

The following project is associated with this  2024 Mill & Pave Program

Carl Road

Scope of Work

From Crowland Road to Morris Road

When will the work take place?

Spring / Summer 2024

Associated Project

The following project is associated with this  2024 Surface Treatment Program

Dorchester Road

Scope of Work

From McLeod Road to Hydro Corridor

Associated Project

The following project is associated with this  2024 Asphalt Overlay Program

Dunn Street

Scope of Work

From Ailantus Street to Orchard Avenue

Associated Project

The following project is associated with this  2024 Mill & Pave Program

Durliat Road

Scope of Work

From Montrose Road to Holloway Bay Rd

When will the work take place?

Spring / Summer 2024

Associated Project

The following project is associated with this  2024 Surface Treatment Program

Garner Road

Scope of Work

From McLeod Road to Warren Woods (Hydro Corridor)

Associated Project

The following project is associated with this  2024 Asphalt Overlay Program

Harleyford Crescent

Scope of Work

Off Sarah Street

Associated Project

The following project is associated with this  2024 Sidewalk Replacement Program

Harleyford Crescent

Scope of Work

Off Sarah Street

Associated Project

The following project is associated with this  2024 Road Rehabilitation Program

Lyons Creek Road

Scope of Work

From Mckenney Road to East Limit

When will the work take place?

Spring / Summer 2024

Associated Project

The following project is associated with this  2024 Surface Treatment Program

Macklem Street

Scope of Work

From Portage Road to Mechanic Street

Associated Project

The following project is associated with this  2024 Mill & Pave Program

Marshall Road

Scope of Work

From Beck Road to West Limit

When will the work take place?

Spring / Summer 2024

Associated Project

The following project is associated with this  2024 Surface Treatment Program

Matthews Drive

Scope of Work

From Montrose Road to Mount Carmel Blvd

Associated Project

The following project is associated with this  2024 Mill & Pave Program

Mckenney Road

Scope of Work

From Lyons Creek Road to Yokom Road

When will the work take place?

Spring / Summer 2024

Associated Project

The following project is associated with this  2024 Surface Treatment Program

Morrison Street

Scope of Work

From Stanley Avenue to Valley Way

Associated Project

The following project is associated with this  2024 Mill & Pave Program

Mount Carmel Boulevard

Scope of Work

From Kalar Road to Montrose Road

Associated Project

The following project is associated with this  2024 Mill & Pave Program

Ort Road

Scope of Work

From Bossert Road to Sauer Road

When will the work take place?

Spring / Summer 2024

Associated Project

The following project is associated with this  2024 Surface Treatment Program

Palmer Avenue

Scope of Work

From Simcoe Street to 420 Bridge

Associated Project

The following project is associated with this  2024 Road Rehabilitation Program

Portage Road

Scope of Work

From Norton Street to Macklem Street

Associated Project

The following project is associated with this  2024 Mill & Pave Program

Prospect Street

Scope of Work

From Drummond Road to Portage Road

Associated Project

The following project is associated with this  2024 Asphalt Overlay Program

Rapelje Street

Scope of Work

Off Sarah Street

Associated Project

The following project is associated with this  2024 Sidewalk Replacement Program

Ridge Road

Scope of Work

From Crowland Road west to tracks

When will the work take place?

Spring / Summer 2024

Associated Project

The following project is associated with this  2024 Surface Treatment Program

Ross Street

Scope of Work

The engineering design for sewer separation, watermain replacement and road reconstruction on Ross Street.

When will the work take place?

Summer 2019

Associated Project

The following project is associated with this  Ross Street Sewer Separation - Design

Sarah Street

Scope of Work

From Harleyford Crescent to East Limit

When will the work take place?

Spring / Summer 2024

Associated Project

The following project is associated with this  2024 Road Rehabilitation Program

Swayze Drive

Scope of Work

From Heritage Drive to Stanley Avenue

Associated Project

The following project is associated with this  2024 Mill & Pave Program

Valley Way

Scope of Work

From Drummond Road to Portage Road

Associated Project

The following project is associated with this  2024 Mill & Pave Program

Victoria Avenue

Scope of Work

Clark Avenue to Stanley Avenue. Design of underground sewer and watermain replacements, full road reconstruction with streetscaping, street furniture and LED street lighting.

Associated Project

The following project is associated with this  pin oak

Willoughby Drive

Scope of Work

From Detenbeck Road to South Limit

When will the work take place?

Spring / Summer 2024

Associated Project

The following project is associated with this  2024 Surface Treatment Program

Yokom Road

Scope of Work

From Crowland Road to Montrose Road

When will the work take place?

Spring / Summer 2024

Associated Project

The following project is associated with this  2024 Surface Treatment Program

Associated Projects

ProjectDetails
pin oak Details
Garner Road Sanitary Extension Design - Black Forest Cr to Forestview BvDetails
Ross Street Sewer Separation - DesignDetails
Asset Management Plan UpdateDetails
Forestview Estates Subdivision Sanitary Sewer and Watermain UpsizingDetails
Beck Road Bridge ReplacementDetails
Drummond Road ImprovementsDetails
Main Street Chippawa Road Reconstruction & Storm Sewer ReplacementDetails
Willoughby Drive ReconstructionDetails
Banting Avenue & Roosevelt Avenue Sanitary Sewer and Watermain ReplacementDetails
Victoria Avenue BridgeDetails
Silvertown Area Functional Servicing Assessment StudyDetails
Chippawa Parkway Culvert ReplacementDetails
Marshall Road Bridge ReplacementDetails
Ort Road Bridge ReplacementDetails
Huron Street Road ReconstructionDetails
Armoury Street Sewer SeparationDetails
Elm Street Sewer SeparationDetails
Homewood Avenue Sewer SeparationDetails
Maple Street Sewer SeparationDetails
Rideau Street Watermain ReplacementDetails
Schisler Road Bridge RehabilitationDetails
Detenbeck Road Bridge ReplacementDetails
Koabel Road Bridge RehabilitationDetails
Major Donald Dell Bridge RehabilitationDetails
Willowdell Road Bridge RehabilitationDetails
Dorchester Road Reconstruction (Oldfield to Mcleod)Details
Dorchester/Oldfield Intersection EA & DesignDetails
Dixon Street Sewer Separation (Level Ave. to Orchard Ave.)Details
Reixinger Road Watermain Loop and Hospital ServicingDetails
Mewburn Road Reconstruction - Mountain Road North to City LimitsDetails
Rural Roads Needs StudyDetails
Whirlpool Road Reconstruction - OPG Canal to Stanley AvenueDetails
Royal Manor Drive Bridge RehabilitationDetails
Willick Road Reconstruction - Sodom Rd. to Ort Rd (Design)Details
Willick Road Box Culvert ReplacementDetails
Ferry Street Reconstruction - Phase 1Details
2024 Asphalt Overlay ProgramDetails
2024 Sidewalk Replacement ProgramDetails
2024 Road Rehabilitation ProgramDetails
2024 Mill & Pave ProgramDetails
2024 Surface Treatment ProgramDetails