Road Rehabilitation & Maintenance

The City of Niagara Falls uses a pavement information system to determine which streets will be capital improvements in any given year. Pavement conditions, pavement age, traffic volumes, timely maintenance and work are all monitored and ultimately influence the timing and need for road rehabilitation projects.

2025 Budget Year will see 16.70 km of roads rehabilitated / reconstructed through the capital programs including road reconstruction, resurfacing, overlay and restoration programs. That includes 9.70 km of Urban Roads reconstructed and / or resurfaced, and 7.0 km of Rural Roads surface treated. Additionally, 2.65 km of sidewalks will be replaced.

The streets selected for road improvements have been listed below. The work on each street will take about six to eight weeks from start to finish. Construction will take place in stages and there may be delays between each stage.

Please note that streets could be added to or deleted from the program without prior notice from the City.

Armoury Street

Scope of Work

St. Lawrence Avenue to Crysler Avenue

When will the work take place?

Spring/Summer 2025

Associated Project

The following project is associated with this  2025 Asphalt Overlay Program

Byng Avenue

Scope of Work

Lundy's Lane to Cook Street

When will the work take place?

Spring/Summer 2025

Associated Project

The following project is associated with this  2025 Urban Surface Treatment Program

Carl Road

Scope of Work

West boundary to Morris Road and Misner Road to Montrose Road

When will the work take place?

Spring/Summer 2025

Associated Project

The following project is associated with this  2025 Rural Surface Treatment Program

Charnwood Avenue

Scope of Work

Tad Street to Hydro Corridor

When will the work take place?

Spring/Summer 2025

Associated Project

The following project is associated with this  2025 Road Rehabilitation Program

Charnwood Avenue

Scope of Work

Tad Street to Hydro Corridor

When will the work take place?

Spring/Summer 2025

Associated Project

The following project is associated with this  2025 Sidewalk Replacement

Cook Street

Scope of Work

Prince Edward Avenue to Highland Avenue

When will the work take place?

Spring/Summer 2025

Associated Project

The following project is associated with this  2025 Urban Surface Treatment Program

Crowland Avenue

Scope of Work

Biggar Road to Carl Road

When will the work take place?

Spring/Summer 2025

Associated Project

The following project is associated with this  2025 Rural Surface Treatment Program

Crysler Avenue

Scope of Work

Simcoe Street to Jepson Street

When will the work take place?

Spring/Summer 2025

Associated Project

The following project is associated with this  2025 Asphalt Overlay Program

Delta Drive

Scope of Work

Montrose Road to Montrose Road

When will the work take place?

Spring/summer 2025

Associated Project

The following project is associated with this  2025 Road Rehabilitation Program

Delta Drive

Scope of Work

Montrose Road to Montrose Road

When will the work take place?

Spring/Summer 2025

Associated Project

The following project is associated with this  2025 Sidewalk Replacement

Depew Avenue

Scope of Work

High Street to Lundy's Lane

When will the work take place?

Spring/Summer 2025

Associated Project

The following project is associated with this  2025 Urban Surface Treatment Program

Division Street

Scope of Work

Highland Avenue to Leonard Avenue

When will the work take place?

Spring/Summer 2025

Associated Project

The following project is associated with this  2025 Urban Surface Treatment Program

Garden Street

Scope of Work

Brookfield Avenue to Dorchester Road

When will the work take place?

Spring/Summer 2025

Associated Project

The following project is associated with this  2025 Asphalt Overlay Program

Grassy Brook Road

Scope of Work

Welland Boundary to East Limit

When will the work take place?

Spring/Summer 2025

Associated Project

The following project is associated with this  2025 Rural Surface Treatment Program

High Street

Scope of Work

Depew Avenue to Dorchester Road

When will the work take place?

Spring/Summer 2025

Associated Project

The following project is associated with this  2025 Asphalt Overlay Program

High Street

Scope of Work

Depew Avenue to Leonard Avenue

When will the work take place?

Spring/Summer 2025

Associated Project

The following project is associated with this  2025 Urban Surface Treatment Program

Leeming Street

Scope of Work

Woodland Boulevard to Leonard Avenue

When will the work take place?

Spring/Summer 2025

Associated Project

The following project is associated with this  2025 Urban Surface Treatment Program

Leonard Avenue

Scope of Work

Lundy's Lane to Division Street

When will the work take place?

Spring/Summer 2025

Associated Project

The following project is associated with this  2025 Urban Surface Treatment Program

Maitland Street

Scope of Work

Highland Avenue to Leonard Avenue

When will the work take place?

Spring/Summer 2025

Associated Project

The following project is associated with this  2025 Urban Surface Treatment Program

Preakness Street

Scope of Work

Montrose Road to Paddock Trail

When will the work take place?

Spring/Summer 2025

Associated Project

The following project is associated with this  2025 Road Rehabilitation Program

Preakness Street

Scope of Work

Montrose Road to Paddock Trail Drive

When will the work take place?

Spring/Summer 2025

Associated Project

The following project is associated with this  2025 Sidewalk Replacement

Woodland Boulevard

Scope of Work

North Limit to South Limit

When will the work take place?

Spring/Summer 2025

Associated Project

The following project is associated with this  2025 Urban Surface Treatment Program

Associated Projects

ProjectDetails
Garner Road Sanitary Extension Design - Black Forest Cr to Forestview BvDetails
Asset Management Plan UpdateDetails
Forestview Estates Subdivision Sanitary Sewer and Watermain UpsizingDetails
Drummond Road ImprovementsDetails
Willoughby Drive ReconstructionDetails
Silvertown Area Functional Servicing Assessment StudyDetails
Marshall Road Bridge ReplacementDetails
Ort Road Bridge ReplacementDetails
Huron Street Road ReconstructionDetails
Elm Street Sewer SeparationDetails
Homewood Avenue Sewer SeparationDetails
Maple Street Sewer SeparationDetails
Rideau Street Watermain ReplacementDetails
Schisler Road Bridge RehabilitationDetails
Detenbeck Road Bridge ReplacementDetails
Koabel Road Bridge RehabilitationDetails
Major Donald Dell Bridge RehabilitationDetails
Willowdell Road Bridge RehabilitationDetails
Dorchester Road Reconstruction (Oldfield to Mcleod)Details
Dorchester/Oldfield Intersection EA & DesignDetails
Dixon Street Sewer Separation (Level Ave. to Orchard Ave.)Details
Reixinger Road Watermain Loop and Hospital ServicingDetails
Mewburn Road Reconstruction - Mountain Road North to City LimitsDetails
Rural Roads Needs StudyDetails
Whirlpool Road Reconstruction - OPG Canal to Stanley AvenueDetails
Royal Manor Drive Bridge RehabilitationDetails
Willick Road Reconstruction - Sodom Rd. to Ort Rd (Design)Details
Willick Road Box Culvert ReplacementDetails
2025 Asphalt Overlay ProgramDetails
2025 Road Rehabilitation ProgramDetails
2025 Rural Surface Treatment ProgramDetails
2025 Urban Surface Treatment ProgramDetails
2025 Sidewalk Replacement Details