Project Description
Part of ongoing sewer separation efforts across the City in order to maintain our Certificate of Authorization to operate combined sewers from the Ministry of the Environment.
Project scope includes sewer separation, watermain replacement and full road reconstruction on Armoury Street from Victoria Avenue to Crysler Avenue. Additional scope will include sewer separation along St. Lawrence Avenue and Crysler Avenue between Simcoe Street and Jepson Street.
Project Cost
Year | Amount |
---|
2020 | $100,000 |
2023 | $2,253,792 |
Project Schedule
2020-2023
Project Contact
Wendy Eitzen
Project Manager
905-356-7521 ext. 4337
Armoury Street
Scope of Work
Between Victoria Ave. and Crysler Ave.
When will the work take place?
Spring / Summer 2023