Project Description

Upgrade building related items at Fire Station #6 located at 8061 Schisler Road. Items identified through Building Condition Assessment reporting and facilities maintenance include; catchbasin repairs, brick repointing on exterior walls, perimeter sealants, flag pole repairs, siren and tower repairs, foundation weeping tile repairs, exterior painting, replace metal doors and frames, replaced forced air heating unit, replace emergency eye wash and shower station, parking lot asphalt placement, and concrete pad for fire truck pump pit area.

Project Cost

YearAmount
2020$127,710

Project Schedule

2020

Project Contact

Jim Huppunen
Facilities Project Manager
905-356-7521 ext. 4701