Notice of Construction - Clifton Hill Sidewalk Widening

Description

The City of Niagara Falls (City) will be Widening Sidewalks on Clifton Hill from Oneida Lane to Falls Avenue.

During the week, Monday morning to Friday afternoon, traffic will be reduced to one lane, eastbound only, to accommodate construction activities. Detour signs will be posted. Two-way traffic will be restored for weekends and holidays.

In accordance with the contract documents, the Contractor, D&R Landscape Group Inc., is required to notify emergency services of their daily operations.

Construction will commence the week of March 23, 2021, and will be continuous until completion, weather permitting. Construction is expected to be complete before May 20, 2021.

For further information you may contact:

Livia McEachern, P.Eng.

Project Manager, Municipal Works-Engineering

City of Niagara Falls

4310 Queen Street, P.O. Box 1023

Niagara Falls, ON L2E 6X5

(905) 356-7521, ext. 4288

[email protected]

Posting Dates

3/12/2021 to 5/31/2021