Project Description
Based on Culvert inspection and due to the condition of the existing pipes, culvert was identified as being in need of replacement as part of City's bi-annual Bridge and Culvert inspection program completed in 2018.
Design in 2020 / 2021.
Construction in 2022
Project Cost
Year | Amount |
---|
2020 | $35,000 |
2022 | $560,000 |
Project Schedule
2020-2022
Project Contact
Nick Golia
Senior Project Manager - Development
905-356-7521 ext 4290