Project Description

2018: Construction of municipal drain, project consultation and final reporting. 2019: Costs associated with a municipal drain report that was approved for construction by the Town of Fort Erie. Costs represent the amount owing for properties in the City of Niagara Falls that are within the watershed (Netherby Road south to Black Creek).

Project Cost

YearAmount
2018$100,000
2019$50,000

Project Schedule

2018/2019

Project Contact

Nick Golia
Senior Project Manager - Development
905-356-7521 ext 4290