Time to process application (to decision): 3 to 4 weeks
| Step | City's Role | Applicants Role | Target Timeline |
|---|---|---|---|
| Application Submission | N/A | Submits:
|
N/A |
| Reviews files (i.e., names, unlocked status) | N/A | 2 days | |
| N/A | Pays required fees | N/A | |
| Assigned to Planner | N/A | N/A | |
| Review for Completeness | Planner reviews for completeness. Confirms Lot/Block within a Plan of Subdivision registered 8 years or more. | N/A | 1 day |
| Circulation (When Complete) |
Planner circulates to internal departments. Note: If resulting merge will not conform to Zoning By-law, a minor variance or zoning by-law amendment required prior to being brought forward to Council. |
N/A | 1 week |
| Council Meeting | Memo and by-law presented for approval. | N/A | 1 week, scheduling will be determined by Council's schedule. |
| Decision letter sent by Planner. | N/A | 1 day | |
| Registration | N/A | Pays registration fee to Legal Services. | N/A |
| Legal Services registers by-law on title. | N/A | 1 day |