Step 1: Complete any applicable agency approvals
To avoid delays, complete all necessary approvals from other regulatory agencies before you apply.
The details and contact information are on the Applicable Law Checklist.
Other approvals might include:
- Niagara Escarpment Commission
- Niagara Peninsula Energy/Ontario Hydro (minimum setbacks from the hydro lines may apply)
- Niagara Peninsula Conservation Authority
- Regional Municipality of Niagara
- Ministry of Transportation or other Ministries
A sign permit is not required if you have received approvals from the following agencies:
- Regional Municipality of Niagara
- Ministry of Transportation or other Ministries
- Niagara Parks Commission
To be exempt from the requirement for a sign permit, you still need to submit the city’s sign permit application along with the approval(s) granted by the other authorities. This is required for our records. Other authorities' approval does not exempt you from obtaining a building permit when needed.